Find a Part Now

BMW Central Building

The BMW Central Building Located in Leipzig, Germany was the winning design submitted for competition by Pritzker Prize winning architect, Zaha Hadid. The central building is the nerve center[1] for BMW's new $1.55 billion complex built to manufacture the BMW 3 Series.[2]

Concept

The BMW factory prior to the construction of the central building existed as three disconnected buildings, each playing an integral part in the production of BMW 3 Series vehicles. These three production buildings were designed in-house by BMW's real estate and facility management group, housing separately the fabrication of raw auto bodies (645,000 square feet (59,900 m2)), the paint shop (270,000 square feet (25,000 m2)), and the final assembly hall (1,075,000 square feet (99,900 m2))[3]. A competition was held for the design of a central building to function as the physical connection of the three units. It also needed to house the administrative and employee needs spaces. Hadid's design took this idea of connectivity and used it to inform every aspect of the new building. It serves as a connection for the assembly process steps and the employees. Designed as a series of overlapping and interconnecting levels and spaces, it blurs the separation between parts of the complex and creates a level ground for both blue and white collar employees, visitors, and the cars.

The building

From a pool of 25 international architects [4], the BMW jury chose the very innovative design of Zaha Hadid as the final piece of the BMW plant in Leipzig, Germany. With no real precedent for her design, Zaha Hadid's Central Building can only be related to the revolutionary and monumental industrial designs of the past including Fiat Lingotto Factory by G. Matté-Trucco and the AEG Turbine Factory in Berlin by Peter Behrens[5]. The BMW Central building is a 270,000-square-foot (25,000 m2) facility that makes up only 250,000 square feet (23,000 m2) of the 540-acre (2.2 km2) campus[6]. Serving 5,500 employees, the building functions as the most important piece of the factory, connecting the three production sheds. Each day, 650 BMW 3 Series sedans[7] pass through the Central Building on an elevated conveyor as they move from one of the three production sheds to the next. Dim blue LED lights highlight the vehicles after each stage, as they exit one of the sheds. These conveyors not only take the vehicles from one production shed to another, but do so directly through all of the functional spaces of the Central Building. The offices, meeting rooms, and public relations facilities[8] are all built around these elevated conveyors, creating an interesting relationship between the employees, the cars, and the public. Not only is the Central Building an office building and public relations center for the factory, it is also a very important piece of the production process at the factory. All of the load-bearing walls, floors, and office levels are made of cast-in-place concrete, while the roof structure is composed of structural steel beams and space frame construction[9]. The facade is clad in simple materials of like corrugated metal, channel glass, and glass curtain walls [10].

The buildings has received numerous architectural awards, including a 2006 RIBA European Award, and was placed on the shortlist for the Stirling Prize.

Diagrammatic Plan Of BMW Central Building Productions Sheds

Quick facts

  • Building Name: BMW Central Building
  • Location: Leipzig, Germany
  • Client: BMW AG, Munich, Germany
  • Architect: Zaha Hadid
  • Building Footprint: 250,000 square feet (23,000 m2)
  • Total Area: 270,000 square feet (25,000 m2)
  • Building Cost: $60 million
  • Groundbreaking: March 2003
  • Completion: May 2005
  • Employees in Factory: 5,500
  • Program: Control Functions, Offices/Admin., Meeting rooms, Cafeteria, Public Relations
  • Parking: 4,100 Spaces
  • Total Complex Cost: $1.55 Billion

[11][12]

Timeline

  • November 2001: Competition Phase #1
  • November 2002: Competition Phase #2
  • March 2002: Jury Decision
  • August 2002: Design Development Completed
  • 2002/2003: Construction Documents Completed/Bidding and Negotiations
  • March 2003: Groundbreaking/Construction Commenced
  • January 2004: Steel Construction Completed
  • March 2004: Building Enclosed
  • June 2004: Car Park Completed
  • September 2004: Central Building Completed
  • May 2005: Landscaping Completed/Central Building Opened

[13]

References

  1. ^ Hadid, Zaha (2006). BMW Central Building. New York, NY: Princeton Architectural Press.
  2. ^ Architectural Record | Project Portfolio | BMW Plant Leipzig, Central Building. Retrieved April 4, 2009, from Architecture Design for Architects | Architectural Record Web site: http://archrecord.construction.com/projects/portfolio/archives/0508BMW.asp
  3. ^ BMW Central Building, Plant Leipzig by Zaha Hadid Architects | Project Portfolio | Architecture-Page. Retrieved April 4, 2009, from Architecture-Page | International resource for architecture and design Web site: https://web.archive.org/web/20090127024530/http://www.architecture-page.com/go/projects/bmw-central-building-plant-leipzig
  4. Barreneche, Raul (2005, August). Zaha Hadid provides the connective tissue for a BMW complex by designing central building that brings People and cars together. Architectural Record, 193(8), 82-91.
  5. (2005, August). Zaha Hadid: BMW Plant Leipzig, Central Building, Leipzig, Germany, 2005.. A + U: architecture and urbanism, 419(8), 66-85.
  • (n.d.). Zaha Hadid Architects. Retrieved April 5, 2009, from : http://www.zaha-hadid.com
  • (n.d.). Zaha Hadid: BMW Central Building, Leipzig, Germany…Amazon.co.uk: Todd Gannon: Books. Retrieved April 5, 2009, from Amazon.co.uk: low prices in Electronics, Books, Music, DVDs & more: https://www.amazon.co.uk/Zaha-Hadid-Central-Building-Architecture/dp/1568985363
  • (2007, April 4). BMW Central Building. Retrieved April 4, 2009, from Architectook: https://web.archive.org/web/20090107070248/http://architectook.net/bmw-central-building/
  • (n.d.). The Tamed Snake - BMW's Central Building in Leipzig. Retrieved April 5, 2009, from DETAIL.de - Architekturportal und Architek: https://web.archive.org/web/20110314215211/http://www.detail.de/rw_5_Archive_En_HoleArtikel_5536_Artikel.htm
  • (n.d.). Zaha Hadid Architects - Central Building . Retrieved April 5, 2009, from Architecture Online: https://web.archive.org/web/20090329095101/http://www.arcspace.com/architects/hadid/bmw_central/bmw_central.html

WHAT ETS OFFERS?

We are a leading provider of Engines and Transmissions. We have provided customers with an unbeatable Price,
Unmatched Quality and excellent Customer Service for 20 years.

FACTORY WARRANTIES

We use only top quality re-manufacturers to supply our clients with professionally re-manufactured Transmissions. All of our transmissions have factory backed warranties.

CERTIFIED AND TESTED

All of our engines and transmissions are rigorously tested and inspected prior to shipping. This allows us to warranty your engine to keep your vehicle on the road for years to come.

ACCESS TO RESELLERS

We provide access to Salvage yards and auto part retailers for automotive engine and transmissions .

Looking For a Specialist
Please Contact Now
1800-385-3915

Looking For a Specialist
Please Contact Now
1800-385-3915

Call us! Get a Price
003
018
114
116
117
132
303
320
321
326
327
328
335
340
501
503
507
600
700
801
802
803
C1
E23
E30
E9
F20
F25
F30
F48
GS
GT
HP4
IV
K1
K75
M
M1
M10
M2
M3
M30
M4
M5
M8
M88
R12
R18
R2
R27
R32
R45
R65
R68
R75
V
VI
VII
X
X1
X2
X3
X4
X5
X6
X7
Z
Z1
Z3
Z8
i
i3
i4
i7
i8
iX
iX1
iX3

PAY SECURELY WITH

Authorize.Net Merchant Visa Logo MasterCard Logo American Express Logo Discover Card Logo
1800-385-3915